The milling, which is the first phase of paving, (has begun). As the streets are in pretty bad shape, the next phase which is patching and leveling may take a while. It is anticipated that the final paved surface will be completed by the end of June. Because of how high the lots are in Birchwood Gardens compared to the roads, the paving work was delayed because of how wet the ground under the pavement was following the extremely wet winter. If they had come in to do the work before it dried out, it would have been a big mess and the work would have taken longer. We agree, this area is definitely in need of paving, and if the weather cooperates, work will begin this week. Thank you for your patience. If you have any additional questions, please let me know. |
|